Building a custom house in Texas takes about 9 to 14 months from the first agreement to move-in on the homes we build north of Houston, and construction itself averages about 210 days. That's the calendar our families plan around, from the first meeting to the day you get the keys.
I'm Fred Loucks, CEO of Dunn & Stone Builders. I joined the company in 2010 as purchasing manager, bought it in 2019, and work with families on plan design. We've built more than 1,000 homes in the Greater Houston area since 1999.
People ask me how long it takes to build a home, and they usually want one number. I give them two: construction time, and the full calendar from the first agreement through design, soils, permits, and the loan.
The 8 to 12 months for a semi-custom home is a generic construction range used for comparison. Our own custom and semi-custom homes average about 210 days of construction from groundbreaking.
We count construction from groundbreaking, with the permit in hand, to delivery. The months before that are design, selections, soils, the construction drawings, the loan, and the permit. Those months still count toward your move-in date.


Near Houston, most of our custom and semi-custom homes take 9 to 14 months from first agreement to keys, with about 210 days of construction once we break ground. Permits, HOA review, clay soil, and rain are the local factors that move that date.
Most county offices near Houston issue a permit in about 2 to 3 weeks. Harris County is stricter on fill dirt and flood maps. Montgomery County is moving in that same direction.
Most of the lots I walk sit on expansive clay. Homes here usually need engineered post-tension slabs. That adds a week or two of site prep compared with a simple slab in a drier market.
Skipping the soils report doesn't save that week. It moves the risk into the foundation.
Montgomery County now rejects incomplete applications, and the wait starts over from the new filing. Send every required page the first time. Montgomery County's permit list is what the county asks for.
If the lot is deed restricted, the HOA's architectural committee also has to approve the plans, and we build that review into your calendar. Those permit and HOA steps also change with an acreage lot vs a subdivision lot.
Inside city limits, such as Houston, Conroe, Huntsville, and Tomball, the permit process has more steps than in the county, so we confirm the jurisdiction during Exploration and build it into your calendar.

The Census number mixes houses built for sale, houses a contractor builds for one family, and houses people build themselves. Those jobs don't run on the same schedule.
The 2025 Census Survey of Construction, summarized by NAHB, puts the national average at 8.8 months from authorization to completion. Authorization to start is 1.4 months. Construction after that is 7.4 months.
Homes built for sale finished in 7.4 months from permit to completion. Contractor-built homes took 11.7 months on that same measure. Owner-built homes took 14.3 months.
All three count from authorization to finish. They don't count construction only.
The survey starts at the permit. It leaves out the months you spend with me on a floor plan, finish selections, a soils report, or a construction loan.
Those months still happen. They just sit outside the survey window.
We start counting construction the day we break ground. Design, soils, permits, and the loan come first, which is why our custom or semi-custom calendar is 9 to 14 months when construction itself averages 210 days.
NAHB's October 2026 builder survey, published November 10, 2026, puts the average single-family home built for sale at 25.3 weeks of construction, about 5.8 months, on a finished lot. That's a production number. It still leaves out design, the soils report, and the loan, which is why a custom calendar runs longer.

A production builder finishes faster because the plan and the crew already exist. They buy materials in bulk. The superintendent has walked that floor plan dozens of times.
Semi-custom work starts from a proven plan, then we change rooms, the elevation, or the finish level. Each change is worth doing when it fits the family.
Each one also adds coordination. I've seen a wall move 2 feet and take a beam, a duct run, and a window order with it.
Fully custom work from a blank sheet runs longer than semi-custom work because every assembly is new to the trades. That's why I start most families from a plan we've already built, then fit it to the lot and the household. Once finishes are chosen on a plan we've already built, we don't have to restart every decision.
If you're still deciding between the two paths, custom and production homes differ in both cost and timeline.

Before we break ground, a Dunn & Stone home moves through four steps: Exploration, Design, the final contract, and Build Documents. On a typical projection those take about 5 to 6 months together, and the 210 days of construction start after them.
Those are the lengths on a typical projection. Your own calendar is set in Exploration, and it gets updated at every step until the house is delivered.
Exploration is a few focused meetings where we check that a plan works on your land and give you early pricing direction before detailed design begins. Lot evaluation comes first, so the lot's fit, drainage, and utilities are on the table before you fall for a layout.
Design is where the floor plan, the elevation, and every selection get settled, in that order. We work the floor plan first, then the elevation, then the exterior and interior selections, and design is complete when the drawings match every decision.
Special-order windows, cabinets, and appliances get ordered during design, so they're already in production when we break ground.
After the final contract, we order the survey and soils report, finish the construction set and foundation plans, and file for the permit while the construction loan closes. On a deed-restricted lot the HOA application goes in here too.
Payments start with the construction draws, the deposit, and the down payment.
Three spots slow a design more than anything else: reopening a floor plan that was already settled, shopping finishes outside the vendors we build with, and saving big changes for the design-complete meeting.
Plan design goes in order, and each decision builds on the one before it. When we circle back to settled decisions, meetings stack up and the schedule slides. It helps to review the drawings at home before design complete, so that meeting confirms the house instead of redesigning it.
Once the contract is signed, later changes become change orders.

Once we break ground, the house moves through foundation, frame, mechanicals, finishes, and closeout. Dates shift from job to job. We still do the steps in the same order.
Locked selections are what keep this table on schedule. Cabinets ordered after the house is framed don't arrive on the week the tile setter is booked.
Those windows hold when the plan stays stable. A longer driveway, a wet slab week, or a cabinet revision stretches one row and pushes every row after it.
We hand over the house after final inspections, plus a certificate of occupancy where the jurisdiction issues one, and a walkthrough with you.
The house follows the same order as the 5 steps to building a custom home, from the first meeting through keys.

On our recent homes, size added weeks, about six from our smallest size band to our largest. Construction averaged about 194 days for homes under 3,000 sq ft, about 207 days from 3,000 to 3,999 sq ft, and about 238 days at 4,000 sq ft and up, and the full calendar for most families is still 9 to 14 months.
These are our own averages from 27 homes we recently delivered, from about 2,400 to 4,400 sq ft, counted from the start of construction to delivery. They are not an industry figure.
A bigger house adds rooms of drywall, tile, and trim, so finishes run longer. The plan's complexity and how settled the selections are can move the date too.
A 2,000 square foot house sits at the small end of what we build, and our recent homes under 3,000 square feet averaged about 194 days of construction once we broke ground. Plan on 9 to 14 months in total, because design, soils, permits, and the loan come first.
On our recent homes between 3,000 and 3,999 square feet, construction averaged about 207 days, or about 7 months, once we broke ground. From the first agreement to move-in, most families plan on 9 to 14 months.
Our recent homes of 4,000 square feet and up averaged about 238 days of construction, or about 8 months, once we broke ground. Add design, soils, permits, and the loan, and most families are on a 9 to 14 month calendar.

Finishes surprise people. On the jobs I run, they take more construction weeks than foundation or framing.
Cabinets, tile, paint, flooring, and fixtures have to work one room at a time. Cabinets take 8 to 12 weeks after you approve the order. That wait starts when the order goes in, not when the installer shows up.
Foundation and framing look farther along than they are. I still have to tell families we have months of work left after the drywall goes up.
Builders nationally say the same. NAHB's October 2026 builder survey found interior finishes take 6.4 weeks on a home built for sale, longer than any other stage, with framing and rough-ins next at 3.7 weeks each.

A calendar can slip. On our jobs, each of the usual slips already has a place in our process, so I don't treat one as a crisis.
The first one I watch is a finish that is still open. Special-order windows, cabinets, and appliances can take 8 to 16 weeks, which is why we place those orders during design. If someone wants a piece from a store our trades don't stock, we find an equivalent our partners already install.
We settle the floor plan first, then the elevation. That keeps design meetings from stacking. If a room still needs another look, we do it before the construction drawings go out.
In our design center we stay with vendors we already build with and warrant. When we sit down for design complete, we walk the drawings against what we already decided. If a bedroom still needs to move, we move it in that meeting, before walls are framed.
If the building-permit application is complete the first time, most county offices near Houston issue that permit in about 2 to 3 weeks. Missing pages make the county reject the application, and the wait starts over.
Site work is easier when we see the lot early. Buried debris, a high water table, or a tricky soils report is easier to handle when we see it before we pour, because we can still change the foundation and the access path.
Bank payments go out on time when the loan is already in place. We close the construction loan during Build Documents, before we break ground, so a crew isn't waiting on the bank.
I also ask families to leave 30 to 60 days between the projected delivery and a lease end, a school start, or a home sale. That extra time covers a wet week or a late inspection.

Most of our custom and semi-custom houses take 9 to 14 months from first agreement to keys. Construction itself runs about 7 months once we break ground. Design, soils, permits, and the loan fill the months before that.
The 2025 Census average is 8.8 months from authorization to finish, with 7.4 months of construction. Homes built for sale finished in 7.4 months.
Contractor-built homes took 11.7 months from permit to completion. Owner-built homes took 14.3 months on that same measure. NAHB's October 2026 survey puts construction alone at 25.3 weeks for a home built for sale.
With us, a custom or semi-custom house usually takes 9 to 14 months from first agreement to move-in. A blank-sheet plan runs longer than a proven plan with locked selections, and those extra months sit in design, soils, permits, and the loan, not only in framing.
On a typical Dunn & Stone projection, Exploration takes about 3 weeks, Design about 3 months, and Build Documents about 6 weeks, so most families spend about 5 to 6 months before construction starts.
Most of our custom and semi-custom homes near Houston take 9 to 14 months from first agreement to move-in, with construction averaging about 210 days once we break ground.
Finishes take the most construction weeks on the houses we build. The trades work in sequence, and a late change in that stretch costs the most time. Foundation and framing move faster than they look.
Production construction usually takes 5 to 8 months. A custom house of typical family size usually needs more than 4 months of construction. When a quote is that short, ask whether it includes design, the soils report, and the permit.
Building a custom house in 3 months is rare, because construction alone on a typical home built for sale averages about 25 weeks nationally. Ours average about 210 days once we break ground, and design and permits come before that.
If the building-permit application is complete the first time, most county offices near Houston issue that permit in about 2 to 3 weeks. Missing pages make the county reject the application, and the wait starts over. If the lot has an HOA, its architectural review is a separate approval.
Buying an existing house usually closes in about 30 to 45 days once your offer is accepted. Building takes longer. It still makes sense when the resale inventory doesn't match the lot or the layout.
If you already own land, the choice is whether to build on land you own or buy a Houston resale.
If you already own a lot and want to build on your lot in the Houston area, or you're comparing a production timeline with a house built around your family, I'd be glad to walk the land with you and put a real calendar on your plan.